Below is the schedule update from the boat ramp contractor for evening work. Night time work is required due to tidal conditions. This work will include excavation and dirt moving. We apologize in advance for the noise.
12/9 – 4 pm to 10 pm- excavation work/site work
12/10 – 4 pm to 11 pm- excavation work/site work
12/11 – 4 pm to 12 pm- excavation work/site work
12/12 – 6 pm to 1 am- excavation work/site work
12/13 – 8 pm to 2 am- excavation work/site work
12/14 – 8 pm to 2 am- excavation work/site work
Christmas week work:
12/21 – 4 pm to 8 pm- excavation work/site work
12/22 – 4 pm to 10 pm- excavation work/site work
12/23 – 4 pm to 11 pm- excavation work/site work
12/24 – Off for Christmas
12/25 – Off for Christmas
12/26 – 6 pm to 1 am- excavation work/site work
12/27 – 8 pm to 2 am- excavation work/site work
12/28 – 8 pm to 2 am- excavation work/site work