Below is a schedule update from the Boat Ramp project contractor:
Barge demobilization, sometime between 1/1/16 and 1/10/16 weather dependent.
Panel installation and general construction schedule:
1/1/16 thru 1/11/16 – limited on site work pending panel delivery, no night work, no ramp closures.
1/11/16 thru 1/14/16 – final grading and setting of first panels, day and night work- 7:30 am to 2:30 am, no ramp closures.
1/11/16 thru 1/31/16 – upland concrete work and site work- 7:30 am to 4 pm, M-F, no anticipated ramp closures.
We’re getting closer! Again, thank you for your patience during the construction period.